Daily Site Report – Transport Hub Dukuh Atas
Progress Snapshot
Work Activities
Manpower & Safety
Total Headcount: 28
Full workforce present. No absenteeism reported.
Incident: Near Miss
Worker slipped due to wet surface. No injury occurred.
PPE Compliance: Partial
Anti-slip mats installed. Supervisor reminded PPE rules.
Issues & Constraints
Type: Material
Description: Delay in delivery of rebar Ø16
Impact: Schedule
Action Taken: Supplier contacted, delivery rescheduled for tomorrow
Status: Monitoring
Summary
Site activities progressed steadily despite minor material delays. Structural works in Zone B continue as planned, while completed slab formwork in Zone A enables preparation for subsequent activities. Safety observations were addressed immediately to prevent recurrence.
Photo Documentation

Column reinforcement works in Zone B

Completed slab formwork in Zone A

Workers wearing PPE on site